Instructions / Assembly

For Professional Electricians
Tips to install electrical service for ChargePoint Home
ChargePoint Home 12: 16A Station
240V, 20A dedicated circuit required.
NEMA 6-20 outlet installed ground pin on top.
ChargePoint Home 25: 32A Station
240V, 40A dedicated circuit required.
NEMA 6-50 outlet installed ground pin on top.
The NEMA outlet should be located 20-26" from the ground. Refer
to the installation template to decide where to install the station.
The power cord will not bend and is only 12" long (as per the
National Electric Code for EV chargers), so ensure the outlet is
installed close enough for the power cord to plug in.
Neutral is not required at the outlet
Install outlet with ground pin on top
CHARGER
12" power cord
20-26" from ground
Start Here for Plug Installation
Tip: Requires a new, dedicated,
non-GFCI two-pole circuit breaker
Tip: Requires a new,
dedicated, non-GFCI
two-pole circuit
breaker