How to Guide
61
Support Guide
Restraint
L/4
(7”)
L/5
(5.6”)
L/5 L/5
L/4
2L/5 L/2
(14”)
(28”)
L
( 30’ Run)
(30’ Run )
(11.2”)
Basic expansion loop requirements for FlowGuard Gold
®
and ReUze
®
CTS CPVC are described below. One or more expansion
loops, properly sized, may be required in a single straight run. The following charts can be used to determine expansion loop
and offset lengths.
Nominal Dia.,
20’ 40’ 60’ 80’ 100’
In.
1
⁄2 16 23 28 32 36
3
⁄4 19 29 33 38 43
1 22 31 38 44 49
1
1
⁄4 24 34 42 48 54
1
1
⁄2 26 37 45 52 59
2 30 42 52 60 67
Expansion Loop Length (L), inches
for
100°F Temperature Change
Length of Run in Feet
LOOP OFFSET CHANGE IN
DIRECTION
Example: Tubing Size = 1/2” Length of run = 60’ L = 28” (from table)
DESIGN & ENGINEERING DATA
Expansion and Contraction of CTS CPVC
ReUze is a registered trademark of Charlotte Pipe and Foundry Company.
FlowGuard Gold is a registered trademark of Lubrizol Corp.
Failure to compensate for expansion and contraction
caused by temperature change may result in system
failure and property damage.
• Do not restrict expansion or contraction. Restraining
movement in piping systems is not recommended and
may result in joint or fitting failure.
• Use straps or clamps that allow for piping system
movement.
• Align all piping system components properly without
strain. Do not bend or pull pipe into position after being
solvent welded.
• Do not terminate a pipe run against a stationary object
(example: wall or floor joist).
• Do not install fittings under stress.