How to Guide

93
INSTALLATION PROCEDURES
• Measuretoverify
that the pipe has
been inserted to
within2”ofthe
insertion line.
• Seetableforrecommendedsetandcuretimes.
• Toensurejointintegrity,onceinsertioniscomplete,the
pulling tool can be used to hold the joint in place dur-
ing set time and also to ensure that the pipe does not
back out.
• Removeexcess
cement from
the exterior. A
properly made
joint will show a
continuous bead
of cement around
the perimeter. If
voids appear suf-
ficient, cement
may not have
been applied and
joint failure may
result.
• Alignallpiping
system compo-
nents properly
without strain.
Do not bend or
pull pipe into po-
sition after being
solvent welded.