User's Manual

Checkpoint Systems, Inc. – Field Service Installation Document – CKP P/N 10073883
Page 6 of 7
Wiring Procedure
1. Connect antenna cable(s) according to Table on page 2. Plug into ANT1 ANT2
connector, then route cable(s) through the clips for strain relief. Dog-bone excess
antenna cable with provided tie wrap.
Figure 2: Antenna Wiring, Primary Connection (Cable Routing on right)
2. If there are peripherals such as a Key Switch or an external scanner Interlock to
connect, use the following table for the wiring pin-out:
3. Connect AC cord to PSU. Connect PSU to chassis rear
DC Input and slide jack behind the strain relief as
shown in Figure 4 below. Route cabling to avoid
snags. If necessary, use tie wrap to bundle excess.
Figure 3: PSU and Regional AC Cord
Pin # Interlock/Alarm (J6) GPIO/12V (J5)
1 INTLK+ GPO RLY
2 GND GPO RLY
3 INTLK (OPTO) GPI+
4 INTLK (OPTO) GND
5ALARM+ +12V
6 ALARM- GND