6 Plug the factory installed connector into the power supply.
The following tasks must be completed by Target IT staff.
1 Target Technician crimps the wires into an RJ-45 surface mount jack.
• Pins 1 and 2 - orange pair - white, orange, white
• Pins 3 and 6 - green pair - white, green, white
• Blue pair and brown pair are not used.
2 Target Technician tests the CAT 5 cable for network connectivity.
Estimated completion time
Conduit preparation will take approximately 120 minutes. This can vary by Checkpoint
contractor.