Project Management/Marketing Scope
Door layouts are reviewed to verify project deliverables.
Checkpoint personnel will be responsible for ensuring that all local building codes are
met.
Checkpoint personnel will remind Target to buy replacement mats (if necessary) and to
ensure they are delivered in time for the upgrade of existing pedestals.
Checkpoint personnel will work with Target to determine which riser baseplate is best
suited for this store location.
As a precautionary measure, Checkpoint personnel will carry a 15 by 10 foot mat to all
installations.
Checkpoint Contractor Scope
The Checkpoint contractor is responsible for the removal of any Alvarado protective
posts that are currently installed for the purpose of protecting the existing EAS
pedestals.
Removing Alvarado posts usually requires that the posts are cut to floor level.
The Checkpoint contractor installs walker duct and power supply boxes.
Optional one or two additional shelves in the ceiling on one side of the entry way can
be built or Checkpoint contractor can attach the 3 power supplies directly to the
studded wall.
The Checkpoint contractor runs the CAT 5 network cable from the power supply to the
floor.
The Checkpoint contractor is responsible for performing floor cuts, as specified by the
Checkpoint Technician.
The Checkpoint contractor is responsible for back filling all floor cuts after all
necessary wiring has been installed by Checkpoint.
When performing floor cuts on ceramic tiled floors, cuts should only be made within
existing grout lines.
Any specific instruction regarding mats, carpets, tiles, and any other special flooring
consideration will come from Target. (___________)
The Checkpoint contractor should be prepared to replace VCT tiles in certain stores.
The tiles will be provided by Target.
Checkpoint Technical Scope
Checkpoint Technician removes all legacy pedestals and related equipment.
Checkpoint Technician is responsible for inserting wiring into 1.00” PVC conduit
(recommended) to run from ceiling to trench. Factory installed connector should remain
at the portion of the PVC pipe nearer the ceiling.
Ensures that both the Cat 5 cable and power wiring is run in the walker duct from base
of stud wall to bottom of each pedestal.
Checkpoint Technician crimps the wires into a connector.