User's Manual
Table Of Contents

4-3 Liberty UHX Upgrade Guide
• Once network connectivity is confirmed by Target, Checkpoint Technician connects
Cat 5 cable and power connection to pedestals.
• All Liberty UHX antennas are installed, configured and tested for full EAS
functionality by the Checkpoint Technician prior to store opening.
• Once EAS functionality of the antennas is confirmed, the Liberty UHX pedestals
will be configured and tuned for full UHF functionality.
• Checkpoint Technician ensures that completed checklist is faxed to Onsite Project
Coordinator and leaves a voice mail message for the Installation Scheduler, Onsite
Project Coordinator, Account Representative and the Project Manager.
Target Technical Scope
• Target is responsible for obtaining replacement mat prior to installation.
• Target IT staff must install router and network connections prior to the start of the
installation by Checkpoint technicians.
• Target IT staff is responsible for running Cat 5 network cable and terminating at the
power supply, installing connectors on the network cable and testing network
connectivity.
System Removal
• Do not remove any systems until the following conditions have been met:
1 The intended Checkpoint shipment is verified.
2 All Checkpoint contractors are present or accounted for, to include the individual
responsible for performing floor cuts, and the flooring contractor.
3 The intended layout is assessed and shown to the Target store manager or person in
charge.
4 Ensure that any new mats do not interfere with the motion of in-swinging doors.
• All removed equipment will be placed in a dumpster or compactor (ask the store
manager or person in charge).
System Installation
• Reference the appropriate configuration drawing later in this document. Each drawing
lists the relative store numbers.
• Systems should not exceed 72” on center.
• If there are layout issues, the store manager or person in charge should be consulted and
given options first. If a decision is not reached then the Onsite Project Coordinator
should be contacted, and then the Target Project Manager.