User's Manual

4-5 Liberty UHX Upgrade Guide
Explanation of negative responses or further comments
Table 4.3
Door installation checklist
Item
#
Door Designation (i.e., North Door)
No? Explain
Below
Customer
Initials
Checkpoint
Initials
Checkpoint
Contractor
Initials
A New layout agreed upon?
B Replacement mat acquired, if necessary
C Existing pedestals removed and disposed of?
D Old drill holes repaired? (if necessary)
E Floor mats removed?
F Alvarado posts removed and disposed of?
G Alvarado bumper post holes filled in? (if necessary)
H New floor channel cut?
I Walker duct and power supply boxes installed?
J Power ran from ceiling to floor?
K Power ran from walker duct to pedestal riser?
L Wires crimped and power connectors installed?
M Cat 5 cable ran and terminated at pedestal riser?
N Floor cut caulked and/grouted?
O Floor covering repaired/installed/replaced?
P Work area is clean and ready for store opening?
Q Pedestals tested and properly functioning for EAS?
R Pedestals tested and properly functioning for UHF?
Explanation of negative responses or further comments
Table 4.2
Door installation checklist
Item
#
Door Designation (i.e., North Door)
No? Explain
Below
Customer
Initials
Checkpoint
Initials
Checkpoint
Contractor
Initials