4. INSTALLATION PROCEDURES
4.1. UNPACKING
Follow these instructions if the unit is crated.
Christie recommends that the unit be moved to the installation site before
uncrating.
1. Be sure container is upright.
2. Open crate and remove packing.
3. Carefully remove unit from crate.
4. Thoroughly inspect unpacked unit for damage that may have occurred during shipping.
Any damage discovered should be reported to the transportation company at
once for inspection and filing of claim.
4.2. INSTALLATION
Place console in intended operating location in projection booth.
4.2.1. LEVELING F EET
Install four (4) leveling feet by screwing one into each of the four corners underneath base
until about 1/2 inch of thread remains exposed. (See Item 8 in Figure 4-1.)
Christie recommends carefully tilting the console to one side to install the
first two feet, then tilting it to the other side to install the other two feet.
An assistant is required to do this safely.