Installation Manual Part 4
Table Of Contents
- Commissioning
- 7.1 Install the Element Management System (EMS)
- 7.2 Install Access Services Network Gateway (ASN-GW) Hardware and Broadband Wireless Gateway (BWG) Software
- 7.3 Add and Configure the BWG to the EMS Server
- 7.4 Authentication, Authorization, and Accounting (AAA) Server Installation
- 7.5 Add and Configure a BWX 8415 Basestation
- 7.6 Power Up and Provision the BWX 8415 Basestation
PRELIMINARY
7-32
BWX 8415 Basestation Installation and Commissioning Guide
OL-19519-01
Chapter 7 Commissioning
7.6.2 BWX 8415 Basestation Bootup
Example 7-5 Continuation of the Boot Process (NEED NEW BOOT SEQUENCE SCREENSHOTS)
Starting BTS L3IfAgent....................Done
Initializing BTS L2 MemPools .............Done
Initializing BTS MacSys...................Done
Initializing RM Helper....................Done
Initializing Mac Resource.................Done
Initializing BTS UCD/DCD Manager..........Done
Initializing BTS Ranging Manager..........Done
Initializing UL MgmtMsg Processor.........Done
Initializing BTS DSx Msg Manager..........Done
Initializing BTS CS Processor.............Done
Initializing BTS MSS Manager..............Done
Initializing BTS CID Manager.............Done
Initializing BTS PDU Processor............Done
Initializing BTS PHY Processor............Done
Initializing BTS SF Manager...............Done
Starting BTS L2AUTHENTICATOR TASK.....................Done
Starting BTS L2 OAM.......................Done
Initializing BTS NBR_ADV Manager..........Done
Starting MakeInstance
Done
Starting BtsL2L3If................Done
Starting BTS L2MAC Rx.....................Done
Starting CDI Nero.........................Done
Starting EtherBridge......................Done
Starting ARP FSM..........................Done
Starting ARP..............................Done
Starting Dpf..............................Done
Starting RME..............................Done
BootlineMask = 5f
EnableFlag = ffc003
Starting PHY Processing...................Done