Ripwave Base Station I&C Guide Navini Networks, Inc.
234 Part #40-00047-00 Rev D v1.0
February 28, 2003
10. Provide BTS installation – Chassis and Cards.
11. Apply power to BTS and perform all power up, BTS calibration verification checks,
commissioning and initial testing of Navini Networks system. May use EMS on local
laptop.
12. With assistance of Client, Perform Drive Test / Coverage Verification.
13. With assistance of Client, perform data rate testing at mutually specified locations – 15
for Omni, 5 for each panel RFS.
14. With client, integrate BTS into backhaul network and verify operation.
15. Closeout / Customer Acceptance package, including inventory of hardware.
16. Navini Networks to provide own tools and test equipment.
17. Clean job site daily.
Client / Contractor Work Items
1. Perform Site survey at each site.
2. Prepare Installation sketch and Bill of Materials (BOM) for each site. Note that these are
not sealed construction drawings.
3. Client / Contractor Site Design and Bid Walk.
4. Material Procurement.
5. Acquire building permits.
6. Inside Network cabling from demark to BTS rack
7. AC power installation (provide dedicated 115 VAC 20 A circuit for each BTS, dual
outlet receptacle).
8. Air conditioning work or other hut electrical work.
9. 24 VDC rectifier installation, cabling to BTS chassis, cabling to AC circuit breaker. Test
24 VDC system (note: do not
apply power to BTS).
10. Mount 19” TELCO rack inside hut (base anchors, or overhead brackets or both)
11. Provide core drilling and furnish and install feed through panel for coax cables, unless
already existing. Seal holes using similar materials to other existing feed-through at each
site.
12. Install grounding inside hut for rack and 24 VDC system. Install ground bus bar inside
hut entry per drawings. Install ground bus bars on antenna structure and ground coax
cables per sketch.
13. Install and apply coax cables and connectors. This includes main coax runs on tower,
plus coax jumpers at antenna and at hut, as specified by drawings. Recommend and
Install all cable hangers and supports, and grounding, per standard practice in use at
tower location. Install surge protectors per design sketches and BOM.
14. Sweep test coax cables at designated sweep frequencies.
15. Install power and data cable from antenna to BTS.
16. Weather seal all outside connections.
17. Recommend, furnish and install mounting structure (arm assembly) to stand-off Navini
RFS from tower. Standoff assembly to include pipe mount for antenna mount. Install
Navini RFS on arm on tower. Connect to coax cables and provide sweep of cable / RFS
assembly. Provide photographic documentation of tower top installation work.
18. Provide equipment and cable labeling as required.
19. Install (2) GPS antennas on ice bridge (or other agreed upon location). Furnish and