User's Manual

Navini Networks, Inc. Ripwave Base Station I&C Guide
Part #40-00047-00 Rev D v1.0 241
February 28, 2003
Item #
Task / Activity Navini Client Other Notes
2 Pull Cables 1
3 Install Connectors and Grounding 1
4 Install Surge Protectors 2 1
5 Test / Sweep Coax 2 1
6 Install mounts / brackets 2 1
7 Install Racks 2 1
8 Electrical power to Rack 1
9 Backhaul to rack 1
10 Environmental (if required) 1
11 Quality Assurance 2 1
12 Inspections / Punch List 2 1
13 Close all Punch List Items 2 1
14 Provide POTS line for technician use 1
EQUIPMENT COMMISSIONING & INTEGRATION
1 Inspect / Test Cabling / Connections 2 1
2 Install Rack Mount Power System / Card Cages 1 2
3 Test DC System 2 1
4 Plug cards in BTS 1
5 Load EMS / Configure 1
6 Boot BTS 1
7 Provision EMS / BTS / CPE 1
8 Test Operation 1
9 Integrate Backhaul 2 1
10 Verify Operation 2 1
11 Router: Configure / test 1