User's Manual
Ripwave Base Station I&C Guide Navini Networks, Inc.
118 Part #40-00047-00 Rev D v1.0
February 28, 2003
8. Conduct full NLOS Location Tests.
9. Send all test results to Navini’s Technical Support for evaluation.
The cycle continues until the performance objectives are reached.
Verify System Operation With Multiple CPE’s
Set up three computers with CPE’s connected to them. Perform file transfers from all three
computers to verify Base Station operation.
Back Up EMS Database
After all system installation and commissioning activities are complete, perform a backup of the
EMS database. The procedure can be found in the EMS Configuration & Alarm Manager (CAM)
User Guide, P/N 40-000-16-00. Place the backup files on a system server where they will be
periodically backed up on a tape drive.
Customer Acceptance
To conclude the installation and commissioning activities, gather all of the required documents
and forms from the installation and commissioning procedures to create a comprehensive system
I&C package. The customer and Navini Networks will sign the Customer Acceptance Form. A
copy of this form is provided in
Appendix I. The signed form and the system I&C package are
provided to the customer. The original, signed Customer Acceptance Form and system I&C
package are stored in the Navini Networks Technical Support database.