User's Manual

Ripwave Base Station I&C Guide Navini Networks, Inc.
20 Part #40-00047-00 Rev D v1.0
February 28, 2003
Figure 2: I&C Process Flowchart
Click here to link to Appendix B
or to Appendix P.
3-Conduct site survey
& complete the
Site
Candidate Evaluation Form
.
Complete the Interference
Analysis/CPE Site Survey
Tool.
6-Develop Bill of Materials
(BOM)
7-Acquire materials
4-Acquire chosen customer
site information
8-Confirm customer
backhaul & EMS Server
Hardware & FTP Server
are installed & operational
2-Generate coverage
prediction map
5-Perform Network
Architecture design
1-Complete Project Plan
for customer
Site Engineering
Appendix B:
Site Candidate
Evaluation Form
End
Sample BoM provided
in Appendix P
3-Conduct site survey
& complete the
Site
Candidate Evaluation Form
.
Complete the Interference
Analysis/CPE Site Survey
Tool.
6-Develop Bill of Materials
(BOM)
7-Acquire materials
4-Acquire chosen customer
site information
8-Confirm customer
backhaul & EMS Server
Hardware & FTP Server
are installed & operational
2-Generate coverage
prediction map
5-Perform Network
Architecture design
1-Complete Project Plan
for customer
Site Engineering
Appendix B:
Site Candidate
Evaluation Form
End
Sample BoM provided
in Appendix P