User's Manual

Navini Networks, Inc. Ripwave Base Station I&C Guide
Part #40-00047-00 Rev D v1.0 21
February 28, 2003
Figure 2: I&C Process Flowchart, cont’d.
Click here to link to Appendix C
.
3-Install & sweep RF
cables. Record results on
RFS System Test Form.
4-Install & sweep
GPS cables
5-Test & install
data/power cable
7-Install BTS chassis
2-Install all system buss
bars & surge protectors
6- If required, install
BTS mounting rack
8-Install & verify
BTS & RFS grounding
A
Installation
Appendix C:
RFS System
Test Form
1-From shipping containers received at
customer site, gather Manufacturing’s inventory
sheet & test data collected from the BTS & RFS
equipment shipped. Verify all equipment arrived,
the test data is available, & serial numbers match
paperwork. Keep as part of customer site records.
3-Install & sweep RF
cables. Record results on
RFS System Test Form.
4-Install & sweep
GPS cables
5-Test & install
data/power cable
7-Install BTS chassis
2-Install all system buss
bars & surge protectors
6- If required, install
BTS mounting rack
8-Install & verify
BTS & RFS grounding
A
Installation
Appendix C:
RFS System
Test Form
1-From shipping containers received at
customer site, gather Manufacturing’s inventory
sheet & test data collected from the BTS & RFS
equipment shipped. Verify all equipment arrived,
the test data is available, & serial numbers match
paperwork. Keep as part of customer site records.