User's Manual
Ripwave Base Station I&C Guide Navini Networks, Inc.
24 Part #40-00047-00 Rev D v1.0
February 28, 2003
Figure 2: I&C Process Flowchart, cont’d.
Click here to link to Appendix E.
5-Verify all cables are
connected
2-Are you using
the customer
EMS Server
?
No
Yes
3a-Install & configure* the Test
EMS Server & Client. Connect
to the BTS.
3b-Install & configure* the
customer EMS Server &
Client. Connect to the BTS.
1-Review customer network plans
(i.e., T1 vs. Ethernet)
6-Power up BTS & reconfigure Boot
Line configuration data through the
serial port.
7-After BTS has been powered up
at least 15 minutes, perform
3 calibrations.
8-Pass
calibration
?
9a-Perform system
troubleshooting procedures.
No
Yes
A
Commissioning
*Appendix E:
Configuration
Data Forms
4-Enter the RFS configuration
by running the RFS script that
shipped with the antenna eqpt.
5-Verify all cables are
connected
2-Are you using
the customer
EMS Server
?
No
Yes
3a-Install & configure* the Test
EMS Server & Client. Connect
to the BTS.
3b-Install & configure* the
customer EMS Server &
Client. Connect to the BTS.
1-Review customer network plans
(i.e., T1 vs. Ethernet)
6-Power up BTS & reconfigure Boot
Line configuration data through the
serial port.
7-After BTS has been powered up
at least 15 minutes, perform
3 calibrations.
8-Pass
calibration
?
9a-Perform system
troubleshooting procedures.
No
Yes
A
Commissioning
*Appendix E:
Configuration
Data Forms
4-Enter the RFS configuration
by running the RFS script that
shipped with the antenna eqpt.