Assembly Instructions
Navini Networks, Inc. Ripwave Base Station I&C Guide
Part #40-00047-00 Rev F v1.0 (TTA) 271
October 23, 2003
Appendix Z: Site Installation Close-out Documentation
List of Documents
When performing a Ripwave Base Station installation, a number of tasks and forms are
completed during the process. The following is a list and a brief description of each of the
closing documents that are either required or optional for completing the Customer Acceptance
of the system once it is commissioned. If the item is designated as REQUIRED it must be sent
back to Navini Technical Services. If a required document cannot be obtained, you must retain
approval in advance from the Manager, Navini Technical Services.
_____ 1. Customer Contact List. REQUIRED (Project Manager & Customer)
_____ 2. Site Candidate Evaluation Form. REQUIRED Drawings/pictures from site.
_____ 3. Drive Instructions & Map to location. REQUIRED
_____ 4. Network Diagram. Optional.
_____ 5. Antenna Power and Cable Selection REQUIRED
_____ 6. Bill of Materials (BoM). REQUIRED This is a list of the physical materials
and their associated quantities that are used to build the site. This list includes
but is not limited to RF cable type and size, RF cable connectors, grounding,
racks, power supplies, RF cable hangers, RFS mounts, and so forth.
_____ 7. Excel Configuration Forms. REQUIRED These forms are created in Excel
spreadsheets and used to plan the system configuration parameters that must be
in place as part of the installation and commissioning of the system. The forms
are filled out according to how the EMS, BTS, Modems, and Global Parameters
are to be configured for this customer site.
_____ 8. RF Plot REQUIRED
_____ 9. Interference Data. Optional.
_____ 10. Interference Analysis Report. REQUIRED if Interfere Data Collected (RF
Planning)
Above information is required before departing to site
_____ 11. RFS System Test Form. REQUIRED This form contains the data that is
captured during the RF sweeps on the Ripwave RFS antenna and RF cables.
_____ 12. Base Station Installation Certification Form. REQUIRED This form
represents the close of a key milestone, the physical installation of the BTS and
RFS. It includes RFS antenna height, azimuth, downtilt, grounding,
weatherproofing, and other information about the site.
_____ 13. Export BTS Data. REQUIRED This is not a form that needs to be completed;
rather, it is data that is captured from the EMS once the Base Station and
Modems have been provisioned. This step should be completed prior to the
Drive Study, and then again prior to the Location (FTP) tests.