Assembly Instructions
Ripwave Base Station I&C Guide Navini Networks, Inc.
272 Part #40-00047-00 Rev F v1.0 (TTA)
October 23, 2003
_____ 14. Export EMS Data. REQUIRED
_____ 15. Export CpeDescriptors (all). Optional.
_____ 16. Base Station Calibration Verification Form. REQUIRED Calibration
Verification is sometimes referred to as the Sanity Test. The form contains the
operational results of the Base Station transmit and receive tests after the
physical installation has been completed and the BTS has been turned on.
_____ 17. Drive Study Form & Data. REQUIRED Also referred to as Drive Test. The
form contains results of driving the coverage area of the installed Base Station
site and capturing sync data on a laptop. The information is provided to Navini
Networks to help tune the RF coverage model. Need Data Constellation Display.
_____ 18. RF Plot Tuned Model. REQUIRED
_____ 19. Location (FTP) Test Form. REQUIRED This form contains data rate
information that is captured during RF throughput testing. The data is captured
at both the EMS and at the Modem location on a laptop. The number of points to
capture is determined by Navini Networks and the customer. Need BTS
Beamforming and Constellation Display.
_____ 20. RMAs. REQUIRED if replaced cards from original shipment
_____ 21. Backup of Customer Deployed EMS Server. REQUIRED
List of Pictures
The following is a list and description of the REQUIRED pictures that Navini Networks
recommends capturing during the installation project. Additional pictures are acceptable.
_____ 1. RFS antenna mounted on the tower or rooftop
_____ 2. Weatherproofed connectors on the back of the RFS antenna
_____ 3. Cable Bend radius on the tower to the RFS
_____ 4. Jumper cable to RF main feeder connections weatherproofed
_____ 5. RF cable strap ground kit installation in all places as required for installation. RF
main feeder runs.
_____ 6. Lower buss bar with lightning protectors (weatherproofed if outside the shelter)
_____ 7. Main feeder to BTS jumper connections
_____ 8. BTS jumper connections to BTS
_____ 9. RFS antenna grounding connections
_____ 10. BTS grounding connections at BTS and buss bar
_____ 11. Power connections to the BTS