10. Provide BTS installation Chassis and Cards.
11. Apply power to BTS and perform all power up, BTS calibration verification checks,
commissioning and initial testing of Navini Networks system. May use EMS on local laptop.
12. With assistance of Client, Perform Drive Test / Coverage Verification.
13. With assistance of Client, perform data rate testing at mutually specified locations 15 for
Omni, 5 for each panel RFS.
14. With client, integrate BTS into backhaul network and verify operation.
15. Closeout / Customer Acceptance package, including inventory of hardware.
16. Navini Networks to provide own tools and test equipment.
17. Clean job site daily.
Client / Contractor Work Items
1. Perform Site survey at each site.
2. Prepare Installation sketch and Bill of Materials (BOM) for each site. Note that these are not
sealed construction drawings.
3. Client / Contractor Site Design and Bid Walk.
4. Material Procurement.
5. Acquire building permits.
6. Inside Network cabling from demark to BTS rack
7. AC power installation (provide dedicated 115 VAC 20 A circuit for each BTS, dual outlet
receptacle).
8. Air conditioning work or other hut electrical work.
9. 24 VDC rectifier installation, cabling to BTS chassis, cabling to AC circuit breaker. Test 24
VDC system (note: do not apply power to BTS).
10. Mount 19” TELCO rack inside hut (base anchors, or overhead brackets or both)
11. Provide core drilling and furnish and install feed through panel for coax cables, unless
already existing. Seal holes using similar materials to other existing feed-through at each
site.
12. Install grounding inside hut for rack and 24 VDC system. Install ground bus bar inside hut
entry per drawings. Install ground bus bars on antenna structure and ground coax cables per
sketch.
13. Install and apply coax cables and connectors. This includes main coax runs on tower, plus
coax jumpers at antenna and at hut, as specified by drawings. Recommend and Install all
cable hangers and supports, and grounding, per standard practice in use at tower location.
Install surge protectors per design sketches and BOM.
14. Sweep test coax cables at designated sweep frequencies.
15. Install power and data cable from antenna to BTS.
16. Weather seal all outside connections.
17. Recommend, furnish and install mounting structure (arm assembly) to stand-off Navini RFS
from tower. Standoff assembly to include pipe mount for antenna mount. Install Navini RFS
on arm on tower. Connect to coax cables and provide sweep of cable / RFS assembly.
Provide photographic documentation of tower top installation work.
18. Provide equipment and cable labeling as required.
19. Install (2) GPS antennas on ice bridge (or other agreed upon location). Furnish and install
any required brackets or pipe mounts. Install GPS coax cables and connectors from GPS