antenna to BTS.
20. Site walk at completion with Client and Navini, create Punchlist; clear applicable punchlist
items.
21. Arrange disposal of trash
22. Provide RF coverage analysis plots before start of installation. Provide model tuning, if
required.
23. Provide architecture document before start of installation, including connection diagram and
logical network element assignments (IP addresses, PVCs, etc.).
24. Set Up and Verify all network equipment and backhaul circuits.
25. Set Up and Verify Operation and connectivity of EMS computer.
26. Provide one resource to assist with drive testing and location data rate testing.
27. Provide all end user / CPE provisioning in EMS after initial testing.
28. Provide all end user interface and troubleshooting.
29. Monitor EMS / alarms. Forward trouble issues to Navini call center.
30. Contractor and Client to provide own tools, computers, and test equipment.