Connection Diagram

Ripwave Base Station I&C Guide Navini Networks, Inc.
116 Part #40-00047-00 Rev F v1.0 (TTA)
October 23, 2003
Item #
Task / Activity Navini Client Other Notes
11 Intra rack cabling S, I
12 Electrical Circuits S, I
13 Electrical wiring from panel to rack S, I
14 Electrical (conduit, distribution panels, etc.) S, I
15 Environmental Equipment S, I
16 Miscellaneous Hardware S
17 BTS cages / cards S, I
18 Network Router S, I
19 Network Ethernet Switch with ATM interface S, I
20 EMS Server / workstation S, I
21 EMS client workstation (for techs) S, I
22 EMS client workstation (for Navini) S, I
23 Server for DHCP and network applications S, I
24 CPE S
25 User PC with Ethernet and/or USB Card S
26 Provide Construction Supervisor
2 1
Navini will supervise
installation of Navini
equipment.
27 Provide Installation Resources
2 1
Client contractors.
Navini will install the
BTS in the client
installed rack/cabinet.
Navini will provide
technical guidance for
installation of the RFS.
CONSTRUCTION
1 Site Preparation / Infrastructure 2 1
2 Pull Cables 1
3 Install Connectors and Grounding 1