Installation Instructions Chapter 1

Ripwave Base Station I&C Guide Navini Networks, Inc.
Chapter 1
2 Part #40-00047-01 Rev F v1.0 (TTA)
October 23, 2003
About This Document
Purpose
This document provides a Navini-certified Installation & Commissioning Technician or Field Engineer with
instructions to properly install the Base Transceiver Station (BTS), Radio Frequency Subsystem (RFS), and cabling;
and to test and commission the Base Station after installation.
Revision History
Date Revision/
Version
Authors Editors Comments
2001 A/1.0 J. Price, C. Keltner, A.Chua,
P. Blain, J. Coulson, D.
Karina, K. Sharp, L. Hoffman
N/A Draft
4.02 B/v1.0 Same N/A Preliminary
8.30.02 C/1.0 Same N/A Prepare for release 1.16
9.3.02 C/1.0 Same S. Redfoot Review comments from class 8.30.02
9.27.02 C/1.0 Same Same Preliminary Commercial Release 1.18
10.18.02 C/1.0 Same Same Feedback on forms and specifications
2.7.03 D/1.0 Same Same Combined all Base Station I&C into
one manual; Preliminary 1.19
2.28.03 D/1.0 Same Same Standard Release 1.19
4.4.03 D/1.0 Same Same File Mngtchanges, no content change
7.30.03 E/1.0 Same + R. Hernandez
E. Curl, M. Johnson
Same Standard Release 1.20
9.12.03 F/1.0 J. Coulson + L. Font L. Font Draft updates for TTA trials
9.27.03 F/1.0 D. Karina, E. Condon S. Redfoot
& L. Font
UL & TTA updates; TOC, Grounding
diagrams (Fig 1, 2, 3), Flow Diagram,
Technical Specs Table, inclinometer
10.04.03 F/1.0 H. Bhakta, Mitch Johnson L.Font Changes required for UL compliance.
2.4 TTA and 3.5 TTA tables added to
Appx O. Page and TOC renumbering.
10.09.03 F/1.0 L.Font Consolidated changes after Oct 9
review. Plurals of acronyms.
10.23.03 F/1.0 J.Coulson, P.Prudhomme,
L.Font
L.Font Some drawing updates pending from
the Oct 9 review. Magnetic Declination
charts update.