Installation Instructions Chapter 1

Ripwave Base Station I&C Guide Navini Networks, Inc.
Chapter 1
24 Part #40-00047-01 Rev F v1.0 (TTA)
October 23, 2003
Figure 4: High Level I&C Process Flowchart
Phase I: Pre-installation - Site Selection, Design & Preparation
1
-
Complete the Project Plan for this
deployment. <Program or Project Manager>
2
-
Generate a coverage prediction map.
<RF Engineering>
3
-
Conduct a site survey, filling out the
Site
Candidate Evaluation Form.
4
-
Complete the
Interference Analysis,
following the Interference Sweep Procedure or,
if available, using the Interference Sweep Tool.
5
-
Acquire information about the final site
selected by the customer. Physical site design
completed.
Appendix D:
Site Candidate
Evaluation Form
Appendix E:
Interference Sweep
Procedure
Appendix F:
Interference Sweep
Tool
Appendix A:
Sample Statement
of Wor
k (SoW)
Appendix B:
Sample Responsibility
Assignment Matrix (RAM)
Appendix C:
Sample Work Breakdown
Structure (WBS)
Appendix G:
BTS Specifications
Appendix H:
RFS Data Sheets
Appendix I:
BTS Outdoor
Enclosure Mfrs.
Appendix J:
Rectifier/BBU
Manufacturers
A
BEGIN
Appendix K:
Sample Base Station
Drawing