Installation Instructions Chapter 1

Navini Networks, Inc. Ripwave Base Station I&C Guide
Chapter 1
Part #40-00047-01 Rev F v1.0 (TTA) 27
October 23, 2003
Phase II: Installation, continued
10
-
Install & verify the DC input power
source to the BTS.
11
-
Install the GPS antennas.
12
-
Sweep the RFS, per the
Single Antenna
Test Procedure. Record the results & the RFS
serial numbers on the RFS System Test Form
(same form as Step 3, Appendix O).
13
-
Install the RFS & surge protectors and
Connect cables to the RFS.
14
-
Sweep the installed RFS & cables to
verify connections & cable loss. Record results
on the RFS System Test Form (same form as
Steps 3 & 11, Appendix O).
15
-
Verify that the digital cards & RF/PA
cards are installed and seated properly.
16
-
Record the serial & version numbers of
the digital and RF/PA cards on the Base
Station Installation Certification Form.
Appendix R:
Sample Tri-sector
BTS Power Drawing
Appendix T:
Base Station
Installation
Certification Form
B
A
Appendix S:
Single Antenna Test
Procedure