Installation Instructions Chapter 1

Ripwave Base Station I&C Guide Navini Networks, Inc.
Chapter 1
28 Part #40-00047-01 Rev F v1.0 (TTA)
October 23, 2003
Phase II: Installation, continued
17
-
If required in the Responsibility
Assignment Matrix (RAM) portion of the
Project Plan, test the backhaul to the customer
demarcation point.
18
-
Provide a printed package of the measured
results and equipment inventory to the
customer on-site.
19
-
Go over the results using the printed
package and obtain customer sign-off on the
completion of the Installation portion of the
work. Use the Base Station Installation
Certification Form for sign-off (same form as
Step 15, Appendix T).