Installation Instructions Chapter 1

Ripwave Base Station I&C Guide Navini Networks, Inc.
Chapter 1
32 Part #40-00047-01 Rev F v1.0 (TTA)
October 23, 2003
Phase III: Commissioning, continued
Yes
19*
-
Validate that the GPS &
Constellation Debugger are installed
and operational on the Drive Study
laptop. Perform a Preliminary Drive
Study. Record the results on the Drive
Study Form.
20
-
Perform the Preliminary LOS Location
(FTP) Test. Complete 3 uploads & 3
downloads at 3 locations. Record the results on
the FTP Test Form.
E
D
No
23
-
R
esults
adequate?
22
-
Send all preliminary test results to Navini
Technical Support for evaluation.
C
*Note: Step 19 is performed
only if no RF plot is available.
Appendix X:
Drive Study Form
Appendix Y:
Location (FTP) Test
Procedure & Form
21
-
Perform the Preliminary NLOS
Location
(FTP) Test. Complete 3 uploads & 3
downloads at 3 locations. Record the results on
the FTP Test Form.
24a
-
Adjust the RF parameters and
troubleshoot. Go back to Step 18,
Perform calibration.