Installation Instructions Chapter 3
Navini Networks, Inc. Ripwave Base Station I&C Guide
Chapter 3
Part #40-00047-07 Rev F v1.0 (TTA) 101
October 9, 2003
Step 6. Click on Air Interface > Layer 1, and then click Calibrate. In the resulting dialog box
(Figure 52), select FULL CALIBRATION and Calibrate.
Figure 52: Calibrate BTS
Step 7. When the Warning window appears (Figure 53), click Yes.
Figure 53: Warning Window
Step 8. The Full Calibration window appears during system calibration (Figure 54). When
calibration is complete, the Full Calibration window changes and displays the finish
time and the result. Click the Close button to close the Full Calibration window. Note
that the result of “Done” does not mean that the system passed calibration.