Pole/Wall Mounting
Pole Mounting With the Mounting Kit
The mounting kit contains a mounting bracket for wall mounting or pole mounting. This kit can be used to install the Cisco
LoRaWAN Interface Module on a pole. It supports metal, wood or fiberglass poles from 2 to 8 inches in diameter.
To mount the Cisco LoRaWAN Interface Module onto a vertical pole, follow these steps:
1. Select a mounting location on the pole to mount the Cisco LoRaWAN Interface Module. You can attach the Cisco
LoRaWAN Interface Module to any pole with a diameter from 2 to 8 inches (5.1 to 20.1 cm).
2. Determine which size of band clamp is needed based on the pole diameter. Slide the two clamps through the top
and bottom set of mounting slots (see Figure 6 on page 14) and mount the bracket to the pole.
3. Wrap the band clamps around the pole and slide them into the second set of top and bottom mounting slots on the
bracket. Lightly tighten the clamps. Only tighten them enough to keep the bracket from sliding down the pole.
4. Screw an M6 bolt into each of the four bolt holes on the back side of the Cisco LoRaWAN Interface Module. Do not
screw the bolt in all the way. Leave a gap of about 1/8" (3.3mm).
5. Position the four bolts on the Cisco LoRaWAN Interface Module into the bracket keyhole slots. Check to be sure that
the Cisco LoRaWAN Interface Module is properly seated in the slots.(See Figure 6 on page 14)
6. The Cisco LoRaWAN Interface Module should be positioned with the LEDs on the bottom to allow viewing from the
ground.
7. Using a 10mm wrench, tighten the four bolts that connect the Cisco LoRaWAN Interface Module to the bracket to a
torque of 40 in-lbs (4.52 N-m).
8. Locate the Cisco LoRaWAN Interface Module to its final position. Tighten the band clamps with the wrench so that
the Cisco LoRaWAN Interface Module does not slide on the pole. Be sure that the clamps are tight enough that the
Cisco LoRaWAN Interface Module does not move.
9. Continue with Grounding the Device, page 15.
Table 4 Materials Needed for Vertical Pole Mounting
Materials Required In Kit
One mount bracket Yes
Four M6 x12mm hex head bolts Yes
Two stainless steel band clamps (adjustable 2"–5", 51–127 mm) Yes
Two stainless steel band clamps (adjustable 5"–8", 127–203 mm) Yes
10 mm box-end wrench No
Shielded outdoor-rated Ethernet (CAT5 or better) cable with 4.3 to 6.5 mm (0.17 to 0.25 inch) diameter
(for IP67 and strength relief)
No
Ground lug (provided with the Cisco LoRaWAN Interface Module) Yes
Ground block and rod No
Crimping tool for ground lug No
#6 AWG ground wire No