Figure 2: High Level I&C Process Flowchart
1 - Complete the Project Plan for this
deployment. <Program or Project Manager>
2 - Generate a coverage prediction map.
<RF Engineering>
3 - Conduct a site survey, filling out the Site
Candidate Evaluation Form.
4 - Complete the Interference Analysis,
following the Interference Sweep Procedure
or,
if available, using the Interference Sweep Tool
.
5 - Acquire information about the final site
selected by the customer. Physical site design
completed.
Site Candidate
Evaluation Form
Interference Sweep
Procedure
Interference Sweep
Tool
Sample Statement
of Work (SoW)
Sample Responsibility
Assignment Matrix (RAM)
Sample Work Breakdown
Structure (WBS)
BTS Specifications
RFS Data Sheets
BTS Outdoor
Enclosures Guide
Rectifier/BBU
Specifications
A
Sample Base Station
Drawing
BEGIN
Phase I: Pre-installation - Site Selection, Design & Preparation