User Manual

Base Station User Manual Navini Networks, Inc.
4 - Install & sweep the RF cables. Record
results on the RFS System Test Form
.
5 - Install & sweep the GPS cables.
6 - Test & install the data/power cable.
7 - If required, install the BTS mounting rack.
8 - Install the BTS chassis.
RFS System
Test Form
Sample Tri-sector
BTS Grounding
Drawing
9 - Install & verify the BTS & RFS grounding.
Chassis Alarms
Information
3 - Cut cables. Install connectors on cables.
Install Connectors on
Cables Procedure
A
2 - Install all system buss bars and surge
p
rotectors.
1 - From the shipping containers received at
the customer site, gather Manufacturing’s
inventory sheet and test data that was collected
before the BTS & RFS equipment shipped.
Verify all equipment arrived (inventory it),
serial numbers match paperwork, and the test
data is available. Keep this as part of the
customer site records.
Phase II: Physical Installation
22 Part #40-00197-00 Rev C v1.0 (1.20)
September 26, 2003