Certification Form
16 - Record the serial & version numbers of
the digital and RF/PA cards on the Base
Station Installation Certification Form.
15 - Verify that the digital cards & RF/PA
cards are installed and seated properly.
10 - Install & verify the DC input power
source to the BTS.
11 - Install the GPS antennas.
14 - Sweep the installed RFS & cables to
verify connections & cable loss. Record results
on the RFS System Test Form (same form as
Ste
p
s 3 & 11, A
pp
endix O
)
.
13 - Install the RFS & surge protectors.
Connect the 9 RF cables & the data/power
cable to the RFS.
12 - Sweep the RFS, per the Single Antenna
Test Procedure. Record the results & the RFS
serial numbers on the RFS System Test Form
(same form as Step 3, Appendix O).
Sample Tri-sector
BTS Power Drawing
Single Antenna Test
Procedure
A
Installation, continued
Part #40-00047-01 Rev C v1.0 (1.20) 23