56 • Chassis and Blade Installation R-Series Data Center Products User’s Guide
6. Remove the 2 Phillips screws retaining the BackPack.
7. Pull the BackPack by the two tabs and remove it from the chassis.
8. Unsnap and remove the black plastic shield from the AC backplane by pulling
upwards on it.
9. Remove the 9 hex head screws from the AC backplane.
10. Remove and discard the AC backplane.
Figure 30 Exploded View of Upgrade Kit Components
11. Install the new R4300 upgrade parts in the chassis.
12. Place the AC backplane module in the chassis and secure it with 4 hex head screws.
13. Insert the R4300 frame into the base of chassis. Ensure that the frame is fully
seated against the AC backplane module. Secure the R4300 frame with 2 hex head
screws in the locations indicated.
14. Insert the AC input module, and secure it with 2 hex head screws.
15. Slide the power supply modules onto the top of the frame. Ensure each unit is
captured on both sides by the guide flanges and is fully seated into the backplane
connectors.
16. Remove the cardboard shipping brace from the fan pack module and install the
fan pack into the chassis. Secure the fan pack with 5 hex head screws to complete
the base R4300 chassis assembly.
17. Connect the power cords supplied with the upgrade kit to appropriate power
source(s).
18. Install the desired modules in the Connect, Management, and Networking Bays,
as described in “Chassis Configuration and Operation” on page 25.
19. Reseat the blades and power up the chassis.
20. Power up the blades.