Specifications

15
GT-PCS Split Units - 60Hz Puron
®
Created: 29 Aug., 2013
Multiple Unit Piping and Flushing
Water Out
Water In
Heat Pump
B
Water Out
Water In
Heat Pump
A
To Ground
Loop
Water Out
Water In
Heat Pump
C
Indoor Loop
Shut-Off Valve
Ground Loop
Shut-Off Valve
Flush
Valve
Size for Heat Pump
‘A’ Flow
Size for ‘A’ + ‘B’ Flow
Size for ‘A’ + ‘B’ + ‘C’ Flow
Size for
Heat Pump
‘C’ Flow
Size for
Heat Pump
‘B’ Flow
Water Out
Water In
Heat Pump
B
Water Out
Water In
Heat Pump
A
To Ground
Loop
Size for Heat Pump
‘A’ Flow
Size for Heat Pump
‘B’ Flow
Size for ‘A’ + ‘B’ Flow
Figure 9a: Multiple Units with Internal Flow Controllers
Figure 9b: Multiple Units with Internal Flow Controllers and External Flushing Valves
Again, ush the loop through the internal ushing valves. This is important as there may be air/debris in the lines from this unit
to the common piping. Once ushing begins the air will be move into the loop and will need to be ushed out. After the loop
is ushed through the second unit, change the ushing valves to ush the second unit. This process should be repeated for
additional units working from the farthest from the loop to the closest to the loop.
This type of application can generally be employed for systems to 12 tons depending on loop design. However, it is important
perform appropriate calculations to con rm that the variable speed pump can provide adequate ow through all heat pumps
against the loop head when all units are operating.
When the number of units or ushing requirements reaches a point where it is no longer feasible to ush through the internal
valves (generally systems of more than 12 tons depending on loop design), external ushing valves should be installed. In this
case, three-way ushing valves should be used or additional isolation valves must be installed to be able to isolate the loop
during ushing.
First, ush the ground loop. The installer should close the indoor loop shut-off valve (or the internal ushing valves in all units)
and open the ground loop shut-off valve to prevent ow through the indoor loop while ushing the ground loop.
Once the ground loop is ushed, close the ground loop shut-off valve and open the indoor loop valve(s) to ush the units and
indoor piping. Remember that there is an internal check valve in the variable speed pump and that backward ow the unit is
not possible.