System information

24
Geothermal Applications
ClimateMaster: Smart. Responsible. Comfortable.
Carefully back ll the boreholes with an IGSHPA approved
Bentonite grout (typically 20% silica sand soilds by weight)
from the bottom of the borehole to the surface. Follow IGSPHA
speci cations for back lling unless local codes mandate
otherwise. When all U-bends are installed, dig the header
trench 4 to 6 feet [1.2 to 1.8 meters] deep and as close to the
boreholes as possible. Use a spade to break through from
ground level to the bottom of the trench. At the top of the
hole, dig a relief to allow the pipe to bend for proper access to
the header. The “laydown” header mentioned earlier is a cost
effective method for connecting the bores. Figure 8 illustrates
common vertical bore heat exchangers.
Use an IGSHPA design based software such as GeoDesigner
for determining loop sizing and con gurations.
Pond/Lake Applications
Pond loops are one of the most cost effective applications
of geothermal systems. Typically 1 coil of 300 ft of PE pipe
per ton [26 meters per kW -- one 92 meter coil per 3.5 kW
of capacity] is sunk in a pond and headered back to the
structure. Minimum pond sizing is 1/2 acre [0.2 hectares]
and minimum 8 to 10 feet [2.4 to 3 meters] deep for an
average residential home. Actual area can be 1500-3000
sq. ft. per ton [39.6 to 79.2 sq. meters per kW] of cooling.
In the north, an ice cover is required during the heating
season to allow the pond to reach an average 39°F [3.9°C]
just below the ice cap. Winter aeration or excessive wave
action can lower the pond temperature preventing ice caps
from forming and freezing, adversely affecting operation of
the geothermal loop. Direct use of pond, lake, or river water
is discouraged because of the potential problems of heat
exchanger fouling and pump suction lift. Heat exchanger
may be constructed of either multiple 300 ft. [92 meter] coils
of pipe or slinky style loops as shown in Figure 9. In northern
applications the slinky or matt style is recommended due
to its superior performance in heating. Due to pipe and
antifreeze buoyancy, pond heat exchangers will need weight
added to the piping to prevent oating. 300 foot [92 meter]
coils require two 4” x 8” x 16” [102 x 203 x 406 mm] blocks
(19 lbs. [8.6 kg] each) or 8-10 bricks (4.5 lbs [2.1 kg] each)
and every 20 ft [6 meters] of 1-1/4” supply/return piping
requires 1 three-hole block. Pond Coils should be supported
off of the bottom by the concrete blocks. The supply/return
trenching should begin at the structure and work toward the
pond. Near the pond the trench should be halted and back
lled most of the way. A new trench should be started from
the pond back toward the partially back lled rst trench to
prevent pond from ooding back to the structure.
Seal and protect the entry point of all earth coupling
entry points into the building using conduit sleeves
hydraulic cement.
Slab on Grade Construction
New Construction: When possible, position the pipe in the
proper location prior to pouring the slab. To prevent wear as
Figure 9: Typical Pond/Lake Loop Con gurations
the pipe expands and contracts protect the pipe as shown
in Figure 10. When the slab is poured prior to installation,
create a chase through the slab for the service lines with 4
inch [102 mm] PVC street elbows and sleeves.
Retro t Construction: Trench as close as possible to the
footing. Bring the loop pipe up along the outside wall of
the footing until it is higher than the slab. Enter the building
as close to the slab as the construction allows. Shield and
insulate the pipe to protect it from damage and the elements
as shown in Figure 11.
Pier and Beam (Crawl Space)
New and Retro t Construction: Bury the pipe beneath the
footing and between piers to the point that it is directly
below the point of entry into the building. Bring the pipe
up into the building. Shield and insulate piping as shown in
Figure 12 to protect it from damage.
Below Grade Entry
New and Retro t Construction: Bring the pipe through the
wall as shown in Figure 13. For applications in which loop
temperature may fall below freezing, insulate pipes at least 4
feet [1.2 meters] into the trench to prevent ice forming near
the wall.
Pressure Testing
Upon completion of the ground loop piping, hydrostatic
pressure test the loop to assure a leak free system.
Horizontal Systems: Test individual loops as installed.
Test entire system when all loops are assembled before
back lling and pipe burial.
Closed Loop Design/Installation Guidelines