User Manual
Table Of Contents
- Contents
- List of figures
- List of tables
- About this document
- ipBTS system overview
- Planning
- ipBTS C30 installation
- RN commissioning
- Requirements
- CLI connection
- Establishing a console connection
- Connecting the laptop to the ipBTS C30
- Downloading and activating new software
- Verifying SNTP time
- Commissioning the ipBTS C30
- Performing Loopback tests
- The loopback test process
- Backhaul loopback testing
- Ethernet loopbacks
- Looping back Ethernet backhaul links
- Looping back at the Ethernet port
- Entering diagnostic mode and configuring test parameters
- Performing external loopback tests on backhaul links
- Troubleshooting failed backhaul links
- Removing physical loopbacks
- Configuring IP on the Ethernet port and laptop
- Establishing the CLI/SSH/Ethernet connection
- Updating node software
- RN hardware components
- RN Specifications
- Hot-swapping ipBTS hardware
- Index
Airvana ipBTS C30 Installation and Commissioning, Release 4.0 2-1
Chapter 2
Planning
Installing and commissioning a ipBTS C30 involves some preparation. This chapter discusses
preparation and has the following sections:
• Requirements on page 2-1
• Power requirements on page 2-1
• Ground requirements on page 2-2
• Environmental requirements on page 2-2
Requirements
This chapter describes the requirements for installation of an ipBTS system. It contains
information about:
• Input power interfaces on page 2-1
• ipBTS operating and storage temperature specification on page 2-2
• ipBTS humidity specifications on page 2-2
• ipBTS altitude specification on page 2-3
Power requirements
The ipBTS C30 requires only one power supply but supports dual DC input power feeds for
power redundancy. Table 2-1 provides the voltage specifications for input power.
Table 2-1. Input power interfaces
Terminals Functions
-48VDC-A Input power, -48VDC
Input power feed A
-48RTN-A Input power, -48VDC return
Input power feed A