COMMISSIONING
1. COMMISSIONING PROCEDURE
When commissioning a new compressor or re-
commissioning a compressor which has been out
of service, carry out the following procedures
before attempting to start:
Note: We recommend that commissioning is
carried out by a CompAir BroomWade distributor.
1.1 Preliminary Checks
1. Check that the isolator switch is locked ‘OFF’
and that all pipework and electrical power
connections are correct and tight.
2. Release
1
/4 turn fasteners and remove the top
and side panels from the compressor.
3. Open the starter door and remove the
perspex safety panel. Check all screws and
connections in the starter area for security.
Check all electrical connections are made
correctly and are tight.
4. Ensure the main supply cables and fuse
ratings comply with regulations.
5. Ensure the control transformer primary
tapping connections are correct for supply
voltage.
6. Ensure main motor thermal overload is set
correctly for motor F.L.C. and supply voltage
(if applicable).
7. Remove panels as required to gain access to
motor connections. Inspect the motor and
wiring connections to make sure they are
correct and secure.
8. Check that all connections on the rear of the
controller are correct and secure.
9. Check that all protective blanks and tapes
have been removed.
10. Check the oil level and if necessary top up
the separator vessel to the correct level with
BroomWade approved lubricant (see
Chapter 7 ‘Maintenance Procedures’ para
3.4.2 ).
11. Refit panels as required. Refit perspex safety
panel in starter compartment and close
starter door.
Note: The drive belt tension is set at the factory
and requires no further attention.
● Refer to the safety procedures before
commissioning the compressor unit.
● Lethal voltages are used in this equipment.
Use extreme caution when carrying out
electrical checks. Isolate the power supply
before starting any maintenance work.
!
WARNING