3. COMMISSIONING CHECK LIST
1. Protective blanks and tapes
removed. ............
2. Pipework connected and checked.
(Isolating valve fitted). ............
3. All electrical connections checked. ............
4. All control system connections
checked. ............
5. Cable and fuse ratings comply with
regulations. ............
6. Control transformer input voltage
set correctly. ............
7. Overload set correct for motor
size and voltage. ............
8. Oil level correct. ............
9. Air-end primed. ............
10. Drive belt tension correct. ............
11. Air-end and motor rotate freely. ............
12. Pressure transmitter calibrated. ............
13. Pressure set-points set. ............
14. Controller model option set. ............
15. Regulation air system isolating
valve open. ............
16. Oil drain valve closed. ............
17. Motor rotation correct. ............
18. Corrosion inhibitor dispersed. ............
19. Compressor operation correct. ............
20. Oil/air fittings checked. ............
21. Oil temperature within limits. ............
22. Emergency stop checked. ............
23. Compressor test run for
30 minutes. ............
24. Oil level topped up. ............
25. All settings and options recorded. ............