30 kW S-BAND/U ANTENNA GROUP
INSTALLATION
8.9 Rev. C
- TB Filter at the inside bottom of the pedestal chassi, Figure
9 (Pedestal), for the 3 phase motor power cores
- TB 1 at the inside left bottom of the transceiver chassi,
according to system drawings relevant to the application of
the 30kW S-Band/U Antenna Group
Terminals, clamps and connectors etc. included in the Installation Kit must be
used. Content of the installation Kit can vary depending on the Application of
the 30kW S-Band Antenna Group. E.g. if Multicore cable is already terminated
in factory corresponding parts are excluded.
For the termination of the Multicore Cable in the External S-Band PSU see
Installation Manual for that unit.
8 .3 .3 .2 Safet y Sw it ch
The safety switch is supplied by the Manufacturer. Cable from the switch
(normally placed at bottom of Radar Antenna mast) to the Transceiver unit is
not included.
- Check the Safety Switch is placed as described in par. 8.3.2
(Manual Installation)
- Connect the two poles of the safety switch, Figure 10 (Safety
Switch), to TB1 SF/SFR placed down left at the inside of the
transceiver chassis (see Figure 7 (Cabling)).
- The cable gland not used must be properly sealed
- Carefully make sure that the switch is closed in ā€œIā€ (On)
position and open in ā€œ0ā€ (Off) position.
8 .3 .3 .3 Per form ance Monit or Arm
- Open the cover of the pedestal
- After mounting the PM-Arm as described in 8.3.2 above
connect the PM-Arm cable to the plug and put it in the
socket at TB1 RM/RM05 on the ANT.SIGN.PCB. placed at
the inside bottom of the pedestal chassis. Figure 9
(Pedestal)
8 .3 .3 .4 Grounding
Connect a tinned braided copper wire (>25mm
2
) between the Ground Terminal
on the Antenna Pedestal and the radar mast.