Lighting Design Guide

Table Of Contents
81
Lighting project checklist
Project Rough-In
Rough-in:
Team: Electrician, Architect,
Interior & Lighting Designer
Electrician performs rough-in of
wiring, panelized cabinets & per
agreed upon architecture
Design topology agreed to by
C4 dealer
Installation conforms to
C4 Reference Guide for
Electricians, local and
national codes
Dealer performs low-
voltage rough-in wiring for
wired keypads
Input Criteria:
C4 dealer completes initial
system design in Control4
Composer and provides
panel, module, & load reports
to electrician
Key Deliverables:
C4 dealer provides panelized
cabinets & terminal blocks to
electrician for installation
C4 dealer orders load control
modules and/or devices
Installation:
Team: Electrician
Who does this? Installation of
modules or individual distributed
load control devices and keypads in
each room as agreed upon by roles
Electrician installs:
AUX override
switch(es) per plan
Initializes panelized lighting
modules with on-device
configuration
Installs all luminaries and
bulbs into each load. All
loads should function, but
not necessarily dim
C4 dealer installs:
Low-voltage wired or
wireless keypads
Input Criteria:
Quality Control (QC) of
installation
Key Deliverables:
Basic Lighting control
is functional
C4 dealer provides modules
and/or devices
System programming:
C4 dealer installs according to the
reference design:
HC based controller
C4 approved router
C4 approved switch
C4 dealer will:
P
rogram and configure the
lighting system
Identify devices into
the system including
load modules/devices
and keypads
Create standard lighting
scenes based upon
final approval
Adjust parameters of
lighting controls including:
cold start, preset levels,
max level
Verify proper dimming
mode on each load:
FWD/REV
Verify proper dimming
of all loads
Input Criteria:
All lighting loads are connected
and operational
Electrician should temporarily
label all loads
Key Deliverables:
A fully functional lighting system
Implementation review:
Team (min): Architect, Lighting
Designer, Electrician
Review luminary and bulb
selection and lighting scenes in
each room
Review use of keypads and
recommend keycap assignment
(custom engraving for
each keypad)
Input Criteria:
Lighting system is fully
functional and programmed
Luminaries and bulbs are
installed per design
Key Deliverables:
Team members agree this
meets objectives of the
project and client review can
be scheduled
Final implementation:
Team (min): Client, General
Contractor or other
decision makers
Final walk thru of lighting
solution by load, by room
Input Criteria:
Client approval of load/keypad
color and finish for keycaps
and faceplates
Receipt of keycaps from C4
Key Deliverables:
Final approval of lighting
solution including: load/keypad
color/finish, lighting scenes,
lighting control
Completed Lighting solutions
binder including:
Keypad programming report
System user manuals
Accounting f
or:
Prompt, detailed of all costs
Variances between
initial estimate
Customer change orders
Device Install Programming Review with Team Client Walk-thru
6
6
8
8
7
7
9
9
5
5
Rough-In
Device Install Review
System
Program
Client
Walk-thru