Unit installation
33
UNIT INSTALLATION
Based on the specific project requirements, choose the type of vibration isolators best suited for the application.
Carefully select the vibration isolators’ models / configuration based on the respective point loads and place each
mount in its correct position following the foregoing Load Distribution Data and Mounting Points Drawing provided
herewith.
Upon completing the mounting of all vibration isolators in their correct positions, move the unit to its installation
location and then lower it carefully in an upright position onto the vibration mounts ensuring that each mount sits in its
correct position with respect to the base rail.
For applications with neoprene pad isolators, equipment and isolators do not require bolting to the concrete base or
substructure. For applications with spring isolators, follow these guidelines:
• Ensure that all vibration isolators get engaged in the mounting holes provided in the unit base rail.
• Follow the specific instructions for levelling, adjustment etc. based on the type of spring isolator employed.
• Isolators should be bolted to the concrete base or substructure and the equipment to isolators.