Unit installation

44
Turn on the chilled water pump, check direction of rotation and adjust the water flow through the cooler to the
specified flow rate. Bleed off all entrained air.
Calibrated pressure gauges have been connected to the suction, discharge and oil pressure ports.
Manually energize the condenser fan starters and check the fan rotation which can be changed on 3-phase motors
by interchanging any two wires on the main terminal block.
Check the power supply voltage. Do not operate the unit if voltage deviation is not within acceptable range
(acceptable voltage range is ± 10% of the rated nominal voltage - temporarily).
Do not utilize generator power for Start-up & Commissioning or Operating
these units, it could be detrimental for this equipment. Consult Zamil for further
information and guidance in this regard.
START-UP OF THE SYSTEM
During Start-up and Commissioning, there should be sufficient heat load to run
the unit under stable full load operation to enable the unit controls, and system
operation to be set up correctly and a commissioning log taken. Ensure that
the Microprocessor Controller is properly programmed - refer to the relevant
section in this manual.
Make use of the Start-up and Commissioning checklist provided in the
Appendix section of this manual for step by step guidelines to accomplish this
task.
Controller Setpoints:
Adjust the controller custom set points as necessary following the instructions given in Microprocessor Controller
section of this manual and ensuring compliance with the requirements. If you are not sure of the appropriate set
points, do not try to change/modify the current set point and contact ZAMIL for guidance.
Start-up:
Start the unit by pushing ON/OFF key in the controller. The ON LED is lit.
After 15 seconds delay, the unit is operational.
At first call for cooling, the controller will de-energize the crankcase heater and start one condenser fan.
After 20 seconds from condenser fan operation, the lead compressor and liquid solenoid valve are operated.
Allow the unit to stabilize and confirm proper operation before moving to SYSTEM CHECKOUT.
To halt the unit, press again ON/OFF key and the ON LED is off.
Notes:
Rate of compressor staging and bringing on more compressors depends on load requirement sensed via
Leaving Water Temperature (LWT).
CAUTION
!
CAUTION
!
(
ATTENTION
(