Installation Manual

Corning Optical Communications
Installation Manual
|
CMA-793-AEN
|
Page
5
Site Considerations
1. The Everon™ 6200 complies with FCC RF exposure limits for an uncontrolled environment. This equipment must be
installed and operated with a minimum distance of 470 cm for HPRU between the antennas and a person’s body.
2. The system delay should be taken into consideration when there are neighboring BTS sites that are overlapping in
coverage. Normal use of the system will not damage the base station; however, with the increase of RU during
network coverage for indoor distribution, the uplink output noise level may affect the sensitivity of the base station,
which should be considered during engineering design. Pick an ideal easy-to-reach location for installation
convenience.
3. Pick an ideal easy-to-reach location for installation convenience.
4. Verify that there is a minimum of a 50 cm radius of space around the Everon™ 6200 equipment for the convenience
of maintenance and on-site inspection.
5. Install the Everon™ 6200 close to the service area for monitor and debugging.
Environmental Considerations
Humidity and temperature can adversely effort reliability of the Everon™ 6200 system. Therefore, it is highly
recommended to install the equipment in locations with stable humidity, temperature, and ventilation.
The equipment has to operate at humidity level and temperature range as follow:
Maximum humidity: 85%
Operating Temperature range: -10°C to +50°C
Storage Temperature range: -25°C to +70°C
DC Power
Connections
Referring to the diagram, connect the power cables as follows:
Higher voltage wire linked to RED cable / Lower voltage wire linked to BLUE cable.