Technical data
44
Figure 4-2 Select grid standard
5.) When the LCD screen shows the normal operation status (Figure 4-3) and
the “RUN” light on the LED panel lights up, it indicates that the grid connection
and power generation are successful.
(a) (b)
Figure 4-3 Normal operation status
6.) If the inverter fails to operate normally, “FAULT” light will light up and the
fault information will show on the LCD screen.
(Please refer to 7.1.2 Troubleshoot LCD faults)
7.) Set up system time and language
Set up the system time and language according to “5.4.4 System
configuration”.
8.) To check the real time operation information, you can refer to “5.4.1
Operation information”.
725 V
38.5A
277
27.9
223.2
PV1
08/12 13:10:05
720 V
31.9A
277
22.9
183.7
PV2
08/12 13:10:10