Bypass Valve Installation - 3/4” Medallist Time Clock
Units Only
The bypass valve connects directly to the backplate of the valve with a pair of
couplings and screws (Figure 14). To facilitate this connection, remove the plate by
pulling up on the u-clip on the back of the valve. Lubricate all o-rings with silicone
lubricant.
Bypass Valve Installation - 3/4” Medallist Soft-Minder
®
Meter Only
The Soft-Minder meter is placed between the bypass valve and the control in place
of the couplings shipped with the Cul-Flo-Valv
®
(Figure 15). Make sure the meter
is on the outlet port of the control and that it is installed with the arrow pointing in
the direction of water ow. A pair of elongated bolts are packaged with the meter
to hold the bypass valve to the back plate of the control. Lubricate all o-rings with
silicone lubricant.
Bypass Valve Installation - 1” Medallist
Plus Units
The bypass valve connects directly to the control valve with a
pair of couplings and two assembly pins (Figure 16). Lubricate
all o-rings on the couplings with silicone lubricant. On Soft-
Minder
®
meter controls, the meter replaces the coupling on
the outlet side of the control. The meter body ts in the same
space as the coupling between the control valve and the
bypass. Make sure that the arrow on the ow meter is pointing
in the direction of ow (Figure 16).
Note: If the ground from the electrical panel or breaker box
to the water meter or underground copper pipe is tied to the
copper water lines and these lines are cut during installation
of the bypass valve, an approved grounding strap must be
used between the two lines that have been cut in order to
maintain continuity. The length of the grounding strap will
depend upon the number of units being installed. In all cases
where metal pipe was originally used and is later interrupted
by the bypass valve to maintain proper metallic pipe bonding,
an approved ground clamp c/w not less than #6 copper
conductor must be used for continuity. Check your local
electrical code for the correct clamp and cable size.
22 Culligan Medallist Series
®
Figure 14
Caution! When reinstalling back plate to control valve, make sure the
u-clip fully engages the two bottom holes of the bracket. Secure bracket
from the top with the two mounting screws provided.
Bypass
Assembly Pin
Coupling
or Meter Body
Coupling
Assembly
Pin
Brine
Connection
Figure 16
Figure 15