3 Pre-Installation Considerations
Before installation begins, certain items must be considered. Prior coordination
reduces delays and the amount of time power has to be interrupted.
Areas of consideration:
No. Description No. Description
1 Generator Set 4 Electrical Meter
2 Propane Tank 5 Natural Gas Meter
3 Transfer Switch
FIGURE 2. SITE PREPARATION EXAMPLE
Location of the generator set - this is one of the first decisions to be made, as it
affects all other aspects of the installation, such as:
Length of electric wiring
Length of gas lines (natural gas or propane - both must be inspected by
the gas utility inspectors and building inspectors)
Site preparation:
Access to the site
Trenches
Site preparation materials needed
Fuel supply pressure
Automatic transfer switch location and connections
Tools and materials required