Use and Care Manual

3. Operation 1-2014
FIGURE 15. GENERATOR SET STATUS SCREEN
3.8 Load Management
The generator set may have been set up at installation to connect and disconnect certain large
loads, such as air conditioners, to manage the total load so as not to overload the generator set.
This requires the installation of relays to the load management signals which allow for the
disconnection of loads. Load management can be set to operate in automatic or manual mode.
Whether in automatic or manual mode, there is a delayed start. Load 1 is enabled three minutes
after the generator set is connected to the house loads, and Load 2 is enabled six minutes after
the generator set is connected to the house loads.