FIGURE 8. CIRCUIT BREAKER AC LOAD CONNECTIONS LOCATION
For connection to the generator set, AC load connections are made in the circuit
breaker box. To access:
1. Remove the enclosure side panel to gain access to main circuit breaker box.
2. Place the circuit breaker handle in the OFF position.
3. Remove the four bolts holding the circuit breaker cover.
4. Install the conductors to the circuit breaker load-side terminals, neutral lug, and
equipment grounding lug.
5. Torque the circuit breaker terminals per specifications on the circuit breaker
label.