Installation manual
■English 6
Refrigerant Piping Work
1.
Installing outdoor unit
1) When installing the outdoor unit, refer to “Precautions for Selecting the Location” on page 2 and the “Indoor/Outdoor Unit 
Installation Drawings” on page 3.
2) If drain work is necessary, follow the procedures below.
2.
Drain work (only heat pump models)
1) Use the drain plug for drainage.
2) If the drain port is covered by a mounting base or floor surface, place 
additional foot bases of at least 30mm in height under the outdoor 
unit’s feet.
3) In cold areas, do not use a drain hose with the outdoor unit.
(Otherwise, drain water may freeze, impairing heating performance.)
3.
Refrigerant piping
 CAUTION
• Use the flare nut fixed to the main unit. (To prevent cracking of the flare nut by aged deterioration.)
• To prevent gas leakage, apply refrigeration oil only to the inner surface of the flare. (Use refrigeration oil for R410A.)
• Use torque wrenches when tightening the flare nuts to prevent damage to the flare nuts and gas leakage.
Align the centres of both flares and tighten the flare nuts 3 or 4 turns by hand. Then tighten them fully with the torque wrenches. 
Drain-water hole
Bottom frame
Drain plug
Hose (available commercially,
inner dia. 16mm)
Do not apply refrigeration 
oil to the outer surface.
Flare nut
Apply refrigeration oil to 
the inner surface of the 
flare.
Do not apply refrigeration oil to 
the flare nut to avoid tightening 
with excessive torque.
[Apply oil]
Flare nut tightening torque 
Flare nut for φ6.4
14.2-17.2N 
 m
  (144-175kgf 
 cm)
Flare nut for φ9.5
32.7-39.9N 
 m
(333-407kgf 
 cm)
Flare nut for φ12.7
49.5-60.3N 
 m
(505-615kgf 
 cm)
Valve cap tightening torque
Liquid side
3/8 inch 1/4 inch
21.6-27.4N 
 m
(220-280kgf 
 cm)
Gas side
1/2 inch
48.1-59.7N 
 m
(490-610kgf 
 cm)
21.6-27.4N 
 m
(220-280kgf 
 cm)
Service port cap tightening torque
10.8-14.7N 
 m (110-150kgf   cm)
01_EN_3P210724-1F.fm Page 6 Tuesday, October 30, 2012 10:39 AM