2MXS18NMVJUA Installation Manual

9 English
Outdoor Unit Installation
4. Pressure test and evacuating system
WARNING
• Donotmixanysubstanceotherthanthespeciedrefrigerant(R410A)intotherefrigerationcycle.
• If refrigerant gas leaks should occur, ventilate the room as soon and as much as possible.
• R410A, as well as other refrigerants, should always be recovered and never be released directly into the environment.
• UseavacuumpumpforR410Aexclusively.Usingthesamevacuumpumpfordifferentrefrigerantsmaydamagethevacuum
pump or the unit.
• When piping work is complete, it is necessary to perform a pressure test
and evacuate system with a vacuum pump.
• If using additional refrigerant, perform air purging of the refrigerant pipes
and indoor unit using a vacuum pump, then charge additional refrigerant.
• Useahexagonalwrench(3/16inch(4mm))tooperatethestopvalverod.
• All refrigerant pipe joints should be tightened with a torque wrench to the
speciedtighteningtorque.
Compound
pressure gauge
Pressure
meter
High-pressure
valve
Low-pressure
valve
Vacuum pump
Service port
Liquid
stop
valve
Valve caps
Gas stop valve
Charging
hoses
Gauge
manifold
1) Pressurize the liquid pipe and gas pipe from the service ports of each stop valve to 550psi (3.8MPa) (do not pressurize
more than 550psi (3.8MPa)) for 1 hour minimum, 24 hours recommended. If there is a pressure drop, check for leaks,
make repairs and perform the pressure test again.
2) Connect projection side of charging hose (which comes from gauge manifold) to gas stop valve’s service port.
3) Fully open gauge manifold’s low-pressure valve (Lo) and completely close its high-pressure valve (Hi).
(High-pressure valve subsequently requires no operation.)
4) Evacuatesystemusingvacuumpumptobelow500micronsfor1hourminimum.
5) Close gauge manifold’s low-pressure valve (Lo) and stop vacuum pump.
(Leave as is for 4-5 minutes and make sure the coupling meter needle does not go back.
If it does go back, this may indicate the presence of moisture or leaking from connecting parts. After inspecting all the
connection and loosening then retightening the nuts, repeat steps 3-5.)
6) Remove covers from liquid stop value and gas stop valve.
7) Turntheliquidstopvalve’srod90°counter-clockwisewithahexagonalwrenchtoopenthevalve.
Close it after 5 seconds, and check for gas leakage.
Usingsoapywater,checkforgasleakagefromindoorunit’sareandoutdoorunit’sareandvalverods.
After the check is complete, wipe all soapy water off.
8) Disconnect charging hose from gas stop valve’s service port, then fully open liquid and gas stop valves.
(Do not attempt to turn valve rod beyond its stop.)
9) Tightenvalvecapsandserviceportcapsfortheliquidandgasstopvalveswithatorquewrenchtothespeciedtorques.
Refer to “3. Refrigerant Piping” on page 8 for details.
01_EN_3P379970-9C.indd 9 10/17/2019 4:42:18 PM