2MXS18NMVJUA Installation Manual
Table Of Contents
- Safety Considerations
- Accessories
- Precautions for Selecting the Location
- Precautions on Installation
- Outdoor Unit Installation Drawings
- Connections (connection port)
- How to Use Reducers
- Installation Guidelines
- Selecting a Location for Installation of the Indoor Units
- Outdoor Unit Installation
- 1. Installing the outdoor unit
- 2. Drain work
- 3. Refrigerant Piping
- 4. Pressure test and evacuating system
- 5. Refilling refrigerant
- 6. Charging with refrigerant
- 7. Refrigerant piping work
- 8. Flaring the pipe end
- Wiring
- Priority Room Setting
- Night Quiet Mode setting
- COOL/ HEAT mode lock
- Pump Down Operation
- Trial Operation and Testing
- 1. Wiring error check
- 2. Trial operation and testing
- 3. Test items
18■English
2. Trial operation and testing
• To test cooling, set for the lowest temperature. To test heating, set for the highest temperature. (Depending on the room
temperature, only heating or cooling (but not both) may be possible.)
• After the unit is stopped, it will not start again (heating or cooling) for about 3 minutes.
• Duringthetestrun,rstchecktheoperationofeachunitindividually.Thenalsocheckthesimultaneousoperationofallindoor
units. Check both heating and cooling operation.
• After running the unit for about 20 minutes, measure the temperatures at the indoor unit inlet and outlet. If the measurements are
above the values shown in the table below, then they are normal.
Temperature difference between
inlet and outlet
About 14°F (8°C)
Cooling
About 36°F (20°C)
Heating
(When running in one room)
• During cooling operation, frost may form on the gas stop valve or other parts. This is normal.
• Operate the indoor units in accordance with the included operation manual. Check that they operate normally.
3. Test items
Are the indoor units installed securely?
Has an inspection been made to check for gas leakage?
Has complete thermal insulation been done (gas pipes, liquid
pipes, indoor portions of the drain hose extension)?
Is the drainage secure?
Are the ground wire connections secure?
Are the electric wires connected correctly?
Is the wiring in accordance with the specifications?
Are the inlets/outlets of the indoor and outdoor units free of any obstructions?
Are the stop valves open?
Do the marks match (room A, room B, room C, room D) on the
wiring and piping for each indoor unit?
Is the priority room setting set for 2 or more rooms?
Test item CheckConsequences of trouble
Fall, vibration, noise
Incomplete cooling/heating function
Water leakage
Water leakage
Electrical leakage
Incomplete cooling/heating function
No operation or burn damage
Incomplete cooling/heating function
Incomplete cooling/heating function
Incomplete cooling/heating function
The priority room setting will not function.
ATTENTION
• Have the customer actually operate the unit while looking at the manual included with the indoor unit. Instruct the customer
howtooperatetheunitcorrectly(particularlycleaningoftheairlters,operationprocedures,andtemperatureadjustment).
• Evenwhentheairconditionerisnotoperating,itconsumessomeelectricpower.Ifthecustomerisnotgoingtousetheunit
soon after it is installed, turn off the circuit breaker to avoid wasting electricity.
• If additional refrigerant has been charged because of long piping, list the amount added on the nameplate on the reverse
side of the stop valve cover.
English
01_EN_3P379970-9C.indd 18 10/17/2019 4:42:20 PM